EcoCité on the Canal Updates
.
October 2006:  

Shortly after the completion of the drilling for the Geothermal wells, Christopher Sweetnam- Holmes gave a brief educational tour to 20-30 people. We invited the public to see the wells before they before buried underneath the building forever. The wells are actually pretty small but those who visited with us seemed really eager to learn about how the system works.

.
September 2006:  

In late September, we started drilling the 14 geothermal wells needed to supply heat for EcoCité on the Canal.

It takes one day to drill each 500-foot well.

To learn about geothermal energy and how it works, please visit the Canadian GeoExchange Coalition website.

.
August 2006:  
site during demolition
site post demolition Any valuable and/or reusable materials in the building had previously been removed from the building, and all remaining materials will be sorted off site for recycling where possible.
.